As of the end of October 2026, two localities had completed the handover of all land required for Phase 1 of the Ho Chi Minh City’s Ring Road 4 project through Dong Nai City, according to the city’s Management Board for Transport Construction Investment Projects on November 2.
![]() |
| Construction on Component Project 1 of the Ho Chi Minh City’s Ring Road 4 project section passing through Hung Thinh Commune, Dong Nai City. |
The two localities that have completed the handover of all land for Phase 1 are An Vien Commune (3.75 hectares), and Binh Minh Commune (more than 22 hectares). In the seven remaining communes and wards traversed by the project, land handover rates for Phase 1 currently range from nearly 87% to more than 99%.
The section of
To implement the project, local authorities and relevant units must acquire more than 443 hectares of land, including over 302 hectares for Phase 1.
For Phase 1, the relevant units have completed 100% of land inventory work and more than 99% of land-origin verification. Compensation and support plans have been approved for nearly 98% of the required land area.
Regarding land handover, the Dong Nai City Management Board for Transport Construction Investment Projects has received more than 285 hectares, equivalent to over 94% of the total land area required for Phase 1.
For Phase 2 site clearance, the relevant units have completed the on-site marking of the land clearance boundaries and handed over the boundary markers to all nine communes and wards. They have also transferred the land acquisition maps and technical records of all nine localities to the
By Pham Tung - Translated by Mai Nga, Thu Ha