Cai Riverside Road targeted for completion in 2026

00:22, 14/10/2026

Construction of the Cai Riverside Road, running from Ha Huy Giap Street to Tran Quoc Toan Street, is being stepped up, with completion targeted for 2026.

Despite prolonged heavy rain, high tides and difficulties in obtaining construction materials, contractors are mobilizing additional workers and equipment and working on multiple sections simultaneously to make up for delays.

The nearly 4.6-kilometer-long, 32-meter-wide Cai Riverside Road has a total investment of nearly VND574 billion. It is one of the key transport projects in central Dong Nai City. Photo: Xuan Luong
The nearly 4.6-kilometer-long, 32-meter-wide Cai Riverside Road has a total investment of nearly VND574 billion. It is one of the key transport projects in central Dong Nai City. Photo: Xuan Luong
Thong Nhat Bridge has opened to traffic, while construction of the Cai Riverside Road continues to gather pace, helping complete the transport network in the area. Photo: Xuan Luong
Construction is proceeding on multiple fronts at the site. For Package No. 28, the contractor has deployed four work fronts, taking advantage of favorable weather to make up for delays. Photo: Xuan Luong
Thong Nhat Bridge has opened to traffic, while construction of the Cai Riverside Road continues to gather pace, helping complete the transport network in the area. Photo: Xuan Luong
Construction is proceeding on multiple fronts at the site. For Package No. 28, the contractor has deployed four work fronts, taking advantage of favorable weather to make up for delays. Photo: Xuan Luong
Construction is proceeding on multiple fronts at the site. For Package No. 28, the contractor has deployed four work fronts, taking advantage of favorable weather to make up for delays. Photo: Xuan Luong
 
Additional equipment and workers have been mobilized along the route, with construction efforts concentrated on construction packages 27 and 28. Photo: Xuan Luong
Additional equipment and workers have been mobilized along the route, with construction efforts concentrated on construction packages 27 and 28. Photo: Xuan Luong
Prolonged periods of heavy rain and high tides have left many sections of the road muddy, disrupting the transport of construction materials, land leveling and other construction activities. Photo: Xuan Luong
Prolonged periods of heavy rain and high tides have left many sections of the road muddy, disrupting the transport of construction materials, land leveling and other construction activities. Photo: Xuan Luong
Work on utility infrastructure is also being expedited alongside road and bridge construction. Power-grid relocation work has reached nearly 87% of the contract value. Photo: Xuan Luong
Work on utility infrastructure is also being expedited alongside road and bridge construction. Power-grid relocation work has reached nearly 87% of the contract value. Photo: Xuan Luong
 
Once completed, the Cai Riverside Road will create a new transport corridor in the city center, improve urban infrastructure, enhance the riverside landscape and provide fresh impetus for Dong Nai Citys socio-economic development. Photo: Xuan Luong
Once completed, the Cai Riverside Road will create a new transport corridor in the city center, improve urban infrastructure, enhance the riverside landscape and provide fresh impetus for Dong Nai City's socio-economic development. Photo: Xuan Luong

By X.Luong – Translated by M.Nguyet, Minho