According to the Civil Aviation Authority of Vietnam (CAAV), by the time
![]() |
| Installation of equipment at the passenger terminal of Long Thanh International Airport. Photo: Pham Tung |
366 flights per week during the initial operating phase
On October 4, at a meeting with a Government working delegation, ACV proposed partially opening
![]() |
| Testing the baggage conveyor system at the Long Thanh International Airport passenger terminal. Photo: Pham Tung |
According to ACV leaders, the airport's opening will follow a phased approach, with operations gradually expanded over time. In Phase 1, from December 2026 to March 2027, the passenger terminal will operate its western wing and central area. Based on flight plans registered by Vietnam Airlines and Vietjet, passenger traffic volume is expected to reach 6–10% of the airport's designed capacity, equivalent to about 20–30 flights per day, focusing on domestic routes and short-haul international routes. The total volume during this period is expected to reach a maximum of 366 flights per week, including 322 domestic and 44 international flights.
“With ACV's strong determination, the CAAV will provide the fullest possible support and take the highest level of responsibility in resolving all procedures in accordance with the law and ICAO standards,” CAAV Director Uong Viet Dung emphasized.
For cargo operations, part of Cargo Terminal 1 will handle domestic cargo starting December 24, 2026. From January 2027, the terminal will begin serving international flights, except those to the European Union (EU) and the
In Phase 2, from April to October 2027, Vietnam Airlines and Vietjet are expected to add international routes to Europe,
During the same period, licensing procedures for the entire airport infrastructure will be completed, while international RA3 certification will be assessed for cargo bound for the EU and TSA requirements for cargo bound for the
In Phase 3, beginning in October 2027, based on the winter flight schedule,
Completing related dossiers on a rolling basis
According to CAAV Director Uong Viet Dung, CAAV is closely following ACV's implementation plan for Component Project 3 at
“CAAV is working alongside ACV on a rolling basis. This means that as each stage is completed, we coordinate with ACV and
![]() |
| Construction of Long Thanh International Airport is being accelerated. Photo: Pham Tung |
Uong Viet Dung added that ACV still has numerous procedures to complete before
The CAAV leader noted that, based on international experience and observations of major airports around the world, bringing a large airport with extensive, highly modern systems, technologies and equipment into operation requires more than the Operational Readiness and Airport Transfer (ORAT) program. Before officially opening, airports typically need six to nine months to conduct trial operations and run their systems smoothly, ensuring that all relevant requirements are fully met.
By Pham Tung - Translated by Mai Nga, Thu Ha