The construction and equipment installation package for the passenger terminal building, regarded as the centerpiece of Phase 1 of the Long Thanh International Airport, is being fast-tracked to meet the timeline for commercial operations.
 |
| Long Thanh Airport’s passenger terminal is designed to international five-star standards, inspired by the image of the lotus flower. |
 |
| The contractor consortium is currently continuing interior ceiling works beneath the skylight layer at the central roof section of the passenger terminal. Photo: Pham Tung |
 |
| Workers complete roof components before installation at the terminal building. Photo: Pham Tung |
 |
| Ceiling installation works are also being carried out simultaneously across multiple levels of the passenger terminal. Photo: Pham Tung |
 |
| Workers install ceiling sections at the second-floor roof area of Long Thanh Airport’s passenger terminal. Photo: Pham Tung |
 |
| Part of the ceiling system at the third-floor central roof section has been largely completed, contributing to the terminal’s modern appearance and architectural aesthetics. Photo: Pham Tung |
 |
| The contractor consortium is simultaneously installing equipment and operational systems for the terminal project. Engineers inspect and compare the ventilation system installation with technical design drawings. Photo: Pham Tung |
 |
| According to the Long Thanh Airport Project Management Board, around 3,000 officials, engineers, and workers are currently involved in construction works at the passenger terminal. Photo: Pham Tung |
 |
| However, construction has encountered certain challenges as the current workforce remains below actual demand. Photo: Pham Tung |
 |
| Despite these difficulties, the Long Thanh Airport Project Management Board has worked with contractors to adjust construction schedules to meet the project’s completion and operational targets. Photo: Pham Tung |
By Pham Tung – Translated by M.Nguyet, Minho