After more than a year of construction, the second runway at Long Thanh International Airport is nearing completion and is expected to be commissioned together with the rest of the airport project.
 |
| The second runway is among the additional investment components incorporated into Phase 1 of the Long Thanh International Airport project. It is being developed to meet operational demand and serve as a backup in case the first runway requires maintenance or experiences technical issues, an essential feature for a high-capacity airport. Photo by Pham Tung. |
 |
| The second runway, under construction since late May 2025, has the same specifications as the first runway, measuring 4 kilometers in length and 75 meters in width. Photo by Pham Tung. |
 |
| According to the Airports Corporation of Vietnam (ACV), construction package No. 4.12, covering the second runway, taxiways and associated facilities, has reached over 60% completion in terms of contract value. Photo by Pham Tung. |
 |
| Contractors are currently focusing on constructing the drainage systems, building service roads and casting concrete structures needed to complete the second runway. Photo by Pham Tung. |
 |
| To keep the project on schedule, contractors have mobilized sufficient manpower, construction machinery and materials for the remaining works under the package. Photo by Pham Tung. |
 |
| The runway pavement structure has already been completed. Installation of the runway lighting system and other operational equipment is scheduled to begin in August 2026. Photo by Pham Tung. |
 |
| According to ACV, concrete paving is expected to be completed by August 15, 2026, with all remaining works scheduled for completion by September 30, 2026. The airport's first runway is already in technical operation after being put into service in late April 2025. Photo by Pham Tung. |