With most of the site clearance completed and the site basically handed over in full, construction of the Cai Riverside Road project is being accelerated. The project is one of Dong Nai City’s key infrastructure projects, being implemented in Tran Bien and Tam Hiep wards.
|
|
|
The Cai Riverside Road section from Ha Huy Giap Street to Tran Quoc Toan Street is nearly 4.6km long and has a 32m-wide roadbed. Construction began in February 2026. Photo: Pham Tung |
|
|
|
Five bridges, including Ba Bot, Chim Tau, Rach Gio, Suoi Linh and Tan Mai, are being newly built along the route. The construction package for the bridges began in late 2023. Photo: Pham Tung |
|
|
|
Workers cast concrete components for the project. Photo: Pham Tung |
|
|
|
Workers install geotextiles to treat weak soil during construction. Photo: Pham Tung |
|
|
|
The Cai Riverside Road project has two road construction packages, with progress currently reaching 14–17% of the contract value. Photo: Pham Tung |
|
|
|
The construction package for the five bridges and approach roads at both ends has reached nearly 90% of the contract value. Photo: Pham Tung |
|
|
|
One section of the project has begun laying crushed-stone aggregate. Photo: Pham Tung |
|
|
|
The site for the entire project has now largely been handed over to construction contractors. Under the signed contract, the Cai Riverside Road project is scheduled for completion by the end of February 2027. However, the project owner and contractors are striving to carry out construction on a rolling basis, with sections where the site is handed over early targeted for completion ahead of schedule by the end of 2026. Photo: Pham Tung |
By Pham Tung – Translated by Mai Nga, Minho