According to the provincial People's Committee, currently, for the construction project of the resettlement area in Tam Phuoc Ward (Bien Hoa City) to serve the resettlement arrangement for the Bien Hoa - Vung Tau Expressway Project, the design drawings and cost estimates have been submitted to the Department of Construction for appraisal.
According to the plan, this resettlement area will commence construction in the first quarter of 2025 and will basically complete the technical infrastructure, handing over the resettlement land to the people in the third quarter of 2025.
Meanwhile, the resettlement area in Phuoc Tan Ward, the second resettlement area serving the resettlement arrangement for the Bien Hoa - Vung Tau Expressway project passing through Bien Hoa City, is also in the process of selecting contractors for surveying and designing construction drawings. This resettlement area is expected to commence construction in the second quarter of 2025 and will basically complete the technical infrastructure, handing over the resettlement land to the people in the fourth quarter of 2025.
Reported by Pham Tung



Thông tin bạn đọc
Đóng Lưu thông tin