Over VND500 bln for 1st phase of Road 768

10:02, 24/02/2016

(ĐN) – On February 23, Vice Chairman Tran Van Vinh of Dong Nai provincial People's Committee presided over a working session with departments and agencies from Vinh Cuu district and Bien Hoa city on Road 768 project invested by Sonadezi Chau Duc J.S Co.

At the working session
At the working session.

(ĐN) – On February 23, Vice Chairman Tran Van Vinh of Dong Nai provincial People’s Committee presided over a working session with departments and agencies from Vinh Cuu district and Bien Hoa city on Road 768 project invested by Sonadezi Chau Duc J.S Co.

At the session, the investor asked for permission to collect tolls for 24 years with current fee levels at VND15,000-120,000 per time. The figure will be VND25,000-140,000 per time in the 2017-2021 period, VND45,000-180,000 in 2027-2031 period, and VND52,000-200,000 since 2031.

The provincial road 768, linking Bien Hoa city and Vinh Cuu district, is constructed under the BOT (Build-Operate-Transfer) model with the total investment of more than VND500 billion.

Reported by H.G