Authorities in Dong Nai are trying to hand over the lands required for the construction of the Phan Thiet – Dau Giay Expressway before the end of May.
Authorities in Dong Nai are trying to hand over the lands required for the construction of the Phan Thiet – Dau Giay Expressway before the end of May.
The sub-department of Land Management said it is working with local authorities and relevant agencies to quickly complete paperwork and procedures to hand over lands to the builder to start construction.
A map showing the route of the Phan Thiet – Dau Giay Expressway, whose construction will begin next quarter. — Photo baobinhthuan.com.vn |
Nguyen Hong Que, head of the sub-department, said a 51.5km portion of the 99km expressway would pass through Dong Nai Province’s Xuan Loc, Cam My and Thong Nhat districts and Long Khanh City.
More than 395 hectares of land have to be acquired from nearly 900 households.
Site clearance has been completed in Cam My and Thong Nhat districts and Long Khanh City, but is proceeding slowly in Xuan Loc District.
The department will co-ordinate with Xuân Lộc District authorities to speed up clearance and compensation payment.
Local authorities have been instructed to complete relocation of infrastructure systems such as power grids, telecom networks and water supply by the end of April.
The Phan Thiet – Dau Giay Expressway is an eastern section of the North-South Expressway, which begins at National Highway 1A in Binh Thuan Province and ends at the HCM City – Long Thanh – Dau Giay Expressway in Dong Nai Province.
Its first phase will cost more than VND14.4 trillion (US$615 million), including VND2.5 trillion ($105 million) from the Government’s coffers and the rest from private investors. It will be built as a public-private partnership under a build-operate-transfer contract.
Construction is scheduled to begin in the third quarter of this year and take 36 months.