Key components of the Long Thanh International Airport project are being accelerated to meet the target of inaugurating Phase 1 on December 19, 2025.
 |
| Runway No.1, which will receive the first flight to land at Long Thanh Airport. Construction units have been focusing on executing the required items in recent months. Photo: Pham Tung |
 |
| Signage along Runway No.1 at Long Thanh Airport has been installed. Photo: Pham Tung |
 |
| The passenger terminal building, the “heart” of Long Thanh Airport, is entering the finishing phase. Many ceiling sections have been completed. Photo: Pham Tung |
 |
| MEPF system’s components (electrical, water supply, ventilation, fire prevention and fighting), as well as ICT and TE (information technology and terminal equipment) for the passenger terminal, are being urgently implemented. Photo: Pham Tung |
 |
| Workers installing passenger boarding bridge components at the Long Thanh Airport terminal. Photo: Pham Tung |
 |
| Installation of stair systems inside the passenger terminal is underway. Photo: Pham Tung |
 |
| Many pieces of equipment for the Long Thanh Airport passenger terminal have been delivered to the construction site by the contractor for installation. Photo: Pham Tung |
 |
| For the construction and equipment installation package of the passenger terminal, the contractor consortium has mobilized nearly 5,000 personnel and more than 1,000 machines and equipment. Photo: Pham Tung |
 |
| The fuel storage system serving Long Thanh Airport operations is being rapidly built. Photo: Pham Tung |
 |
| To meet the goal of inaugurating the project on December 19, 2025, the Long Thanh Airport project continues to operate on a “three-shift, four-team” schedule. Photo: Pham Tung |
 |
| At Component Project 1, many headquarters of state management agencies have basically been completed. Photo: Pham Tung |
 |
| Construction of the two airport connection roads (T1, T2) has been completed. Photo: Pham Tung |
 |
| With the efforts of the investor and contractors, Long Thanh Airport Phase 1 is ready for inauguration on December 19, 2025. Photo: Pham Tung |
By Pham Tung – Translated by M.Nguyet, Thu Ha
Thông tin bạn đọc
Đóng Lưu thông tin