On September 16, Deputy Secretary of the Provincial Party Committee and Chairman of the Dong Nai People’s Committee Vo Tan Duc, together with Member of the Provincial Party Committee and Vice Chairman of the Dong Nai People’s Committee Ho Van Ha co-chaired a working session with relevant agencies to review the progress of public investment disbursement in 2025, the medium-term public investment plan for 2026–2030 period, and the resettlement area development plan for 2026–2030 period.
![]() |
| Deputy Secretary of the Provincial Party Committee and Chairman of the Dong Nai People’s Committee Vo Tan Duc delivers the concluding remarks at the working session. Photo: Pham Tung |
According to the Department of Finance (DoF), as of September 10, the total public investment capital for 2025 assigned by the Provincial People’s Committee reached more than VND 35.6 trillion (excluding extended capital plan). Of this, more than VND 31.9 trillion was assigned by the Prime Minister, and an additional VND 3.7 trillion was allocated by the province. By that date, over VND 11.8 trillion had been disbursed, equivalent to more than 37% of the plan. Excluding more than VND 9.2 trillion from the Gia Nghia–Chon Thanh Expressway project (with disbursement duration allowed to be extended until the end of 2026) and the drainage system project outside Long Thanh International Airport, the province’s disbursement rate reached more than 52%.
![]() |
| A representative of the DoF reports at the working session. Photo: Pham Tung |
Despite drastic instructions from the Provincial People’s Committee and significant efforts by relevant agencies, the disbursement rate of public investment capital has yet to meet expectations.
Regarding the medium-term public investment plan for 2026–2030 period, preliminary reports estimate a total of over VND 147 trillion in capital for the province during this period.
Regarding the plan to develop resettlement areas across the province, according to the Provincial People’s Committee, aggregated reports from localities show that the demand for resettlement to serve projects and works in the 2026–2030 period is more than 47,000 plots of land, with each resettlement plot expected to cover an average area of 100 square meters.
In his concluding remarks, Chairman of the Provincial People’s Committee Vo Tan Duc emphasized that as required by the Prime Minister, Dong Nai, like other provinces nationwide, must achieve 100% disbursement of public investment capital in 2025.
To meet this target, Chairman Vo Tan Duc requested the units with large capital allocations in 2025 to urgently review projects with high disbursement potential and report projects unlikely to disburse on time to the DoF within September 2025. The DoF will advise the Provincial People’s Committee on making internal adjustments to projects in order to accelerate the disbursement of public investment capital.
At the same time, it is necessary to promptly draw up a new critical path for all ongoing projects, along with identifying existing difficulties and obstacles, in order to address them in a timely manner.
Departments of Construction, Agriculture and Environment, Industry and Trade, along with other relevant agencies, were directed to continue applying the “green lane” mechanism throughout project appraisal and approval procedures to minimize administrative processing time as much as possible.
Identifying land clearance as the major bottleneck affecting disbursement progress, Chairman of the Provincial People’s Committee Vo Tan Duc stressed that units and localities must consider site clearance as the decisive link in the whole public investment process. Therefore, it is necessary to act swiftly and decisively in compensation and site clearance work to promptly hand over the land to construction units for project implementation. “Without cleared land, there will be no project,” Chairman of the Dong Nai People’s Committee Vo Tan Duc stressed.
By Pham Tung-Translated by M.Nguyet, Thu Ha







Thông tin bạn đọc
Đóng Lưu thông tin