Site clearance for Bien Hoa City Central Axis Road Project set for completion in October 2025

Translated by: Mai Nga – Thu Ha
17:38, 12/09/2025

To implement the Bien Hoa City Central Axis Road Project, authorities have to revoke over 33ha of land. Of these, more than 27ha of land belong to 390 households, individuals, and organizations.

Construction of the roundabout between branch 1 and branch 2 of the Bien Hoa City Central Axis Road Project. Photo: Pham Tung
Construction of the roundabout between branch 1 and branch 2 of the Bien Hoa City Central Axis Road Project. Photo: Pham Tung

Nguyen Duy Tan, Chairman of Tran Bien Ward People's Committee, stated: Currently, Tran Bien Ward is coordinating with the Bien Hoa-based Land Fund Development Center to accelerate compensation and site clearance for the Bien Hoa City Central Axis Road Project with the goal of completion in October 2025.

The Bien Hoa City Central Axis Road Project has a total length of over 5.4km, divided into 2 branches: Branch 1 is over 3.7km long, starting at the intersection with Vo Thi Sau Street and ending at the intersection with Dang Van Tron Street at the An Hao bridge interchange; Branch 2 is over 1.7km long, starting at the roundabout intersecting with Branch 1 at Hiep Hoa Islet and ending at the intersection with Dang Van Tron Street at the Buu Hoa bridgehead interchange.

According to Tran Bien Ward People's Committee, for Branch 1, the section from Thong Nhat Bridge to Do Van Thi Street, is currently hindered by the premises of only one household and one organization. It is expected that in September 2025, compensation for this area will be completed for handover to the construction unit.

Meanwhile, for the sections from Do Van Thi Street to the An Hao bridge interchange and the Buu Hoa bridgehead interchange, compensation and site clearance are expected to be completed in October 2025.

The Bien Hoa City Central Axis Road Project section from Vo Thi Sau Street to Dang Van Tron Street includes the Thong Nhat Bridge and connecting roads at both ends of the bridge. The project has a total investment of over 1.5 trillion VND with ground broken for construction in 2022. Currently, the entire project has 8 main construction and installation packages being implemented with a realized value of nearly 609 billion VND.

By: Pham Tung