(ĐN)- According to Dong Nai Project Investment Management Board, Dong Nai province's People's Committee has assigned the board as the investor of the flood-prevention project at Bien Hung crossroad.
(ĐN)- According to Dong Nai Project Investment Management Board, Dong Nai province’s People’s Committee has assigned the board as the investor of the flood-prevention project at Bien Hung crossroad.
As planned, the project will be carried out in late 2017 and is expected to be completed in late 2018 under public investment model. The total investment for the project is estimated at VND112 billion.
Flooding occurs frequently at the Bien Hung intersection, causing traffic jams and affecting people lives in the rainy season.
Reported by K.M