(ĐN)- Dong Nai Power Company (DNPC) has recently placed into operation the 110kV Long Thanh-Nhon Trach power line and the Ong Keo 110kV transformer station in Nhon Trach district.
(ĐN)- Dong Nai Power Company (DNPC) has recently placed into operation the 110kV Long Thanh-Nhon Trach power line and the Ong Keo 110kV transformer station in Nhon Trach district.
Started construction in early 2008, the power line and the transformer station were built at a cost of more than VND200 billion with a total length of nearly 14 kilometres.
The new power system is expected to provide adequate supply for Ong Keo and New Nhon Trach industrial parks, contributing to the economic development in Nhon Trach.
DNPC will put into operation one 110kV power line and four 110kV transformer stations by 2020.
Reported by M.A