On December 16, Dong Nai Power Company Limited (PC Dong Nai) held an inauguration ceremony for the 110kV Long Thanh Airport substation and its associated connection lines. The project will supply electricity directly to Long Thanh International Airport.
![]() |
| Truong Dinh Quoc, Secretary of the Party Committee and Director of PC Dong Nai, delivers a speech at the inauguration ceremony. Photo: Hoang Loc |
Attending the ceremony were Duong Minh Dung, Member of the Standing Board of the provincial Party Committee, Secretary of the Party Committee and Chairperson of the People’s Council of Long Thanh District; Vu Ngoc Long, Member of the provincial Party Committee and Director of the provincial Department of Industry and Trade; and Bui Quoc Hoan, Deputy General Director of Southern Power Corporation.
The 110kV Long Thanh Airport substation has a total capacity of 80 MVA, with an investment exceeding VND 158 billion. It is designed to meet the standards of an unmanned substation. The entire monitoring and control system has been digitised and is operated remotely, enabling real-time equipment condition monitoring and ensuring the highest level of reliability in power supply.
![]() |
| Delegates attend the inauguration ceremony. Photo: Hoang Loc |
The completion of the project plays an important role in ensuring a continuous, high-quality electricity supply for the operation of Long Thanh Airport. It also helps reduce the 22kV power supply radius, minimise power losses, stabilise voltage quality, and enhance the reliability of electricity supply for surrounding areas.
![]() |
| Vu Ngoc Long, Director of the Dong Nai Department of Industry and Trade, delivers remarks on behalf of the provincial People’s Committee at the ceremony. Photo: Hoang Loc |
According to Truong Dinh Quoc, Secretary of the Party Committee and Director of PC Dong Nai, the project is large in scale, requires advanced technical standards, strict safety measures, and was implemented under a tight construction schedule, with coordination among many units both within and outside the power sector. The commissioning of the 110kV Long Thanh Airport substation not only adds a major power facility to Dong Nai Province but also carries special significance. The project ensures a stable, continuous, and high-quality power supply for critical airport facilities, including air traffic management systems, runway and taxiway lighting, passenger terminals, security screening systems, technical centres, and auxiliary infrastructure.
For employees of the company, this is a great source of pride, as they have contributed directly to a national key project that meets the stringent technical requirements of the country’s largest international airport.
![]() |
| Bui Quoc Hoan, Deputy General Director of Southern Power Corporation, delivers congratulatory remarks. Photo: Hoang Loc |
Vu Ngoc Long emphasised that Long Thanh Airport is a national key project and embodies the development aspirations of Dong Nai Province and the southern key economic region. The 110kV substation is not only a supporting technical facility but also a crucial project with a significant impact on the airport's construction progress and operational quality.
The PC Dong Nai’s successful completion of both investment phases and the connection to the airport’s internal power grid just ahead of the first technical flight, scheduled for December 19, is of great importance.
![]() |
| Leaders of departments, sectors, local authorities, and the power sector perform the ribbon-cutting ceremony. Photo: Hoang Loc |
![]() |
| Leaders of departments, sectors, local authorities, and the power sector congratulate on the completion of the project. Photo: Hoang Loc |
The Director of the Department of Industry and Trade noted that the external power supply infrastructure serving the airport will also act as a "lifeline" driving the development of an integrated chain of urban, industrial, and logistics zones in the surrounding area in the future. He called on PC Dong Nai to ensure the facility's safe, stable, and continuous operation. The Department will continue to coordinate with the power sector to review and forecast electricity demand, prepare power grid infrastructure for future expansion phases of the airport and neighbouring areas, and ensure that power infrastructure keeps pace with urban, industrial, and logistics planning.
![]() |
| Bui Quoc Hoan, Deputy General Director of Southern Power Corporation, presents commendations to collectives and individuals for completing the project ahead of schedule. Photo: Hoang Loc |
He also urged the Airports Corporation of Vietnam to closely coordinate with PC Dong Nai to connect and operate the internal power system to ensure synchronisation, while regularly reviewing load demand and developing long-term power supply scenarios to meet the airport's future development needs.
At the same time, Southern Power Corporation and PC Dong Nai were encouraged to continue allocating resources and accelerating power projects in line with Dong Nai Province's planning, with the aim of developing a modern, intelligent power grid that meets the requirements of rapid, sustainable development.
![]() |
| PC Dong Nai workers conduct technical inspections before energisation. Photo: Hoang Loc |
On this occasion, Southern Power Corporation and PC Dong Nai awarded commendations to several collectives and individuals for their outstanding achievements in completing the 110kV Long Thanh Airport substation and its connection lines ahead of schedule.
By Hoang Loc - Translated by My Le, Thu Ha