Efforts to complete site clearance for expressway project

04:08, 07/08/2012

(ĐN)- Dong Nai province People’s Committee on August 6 organized a meeting to solve site-clearance problems related to the HCMC-Long Thanh-Dau Giay expressway project.

(ĐN)- Dong Nai province People’s Committee on August 6 organized a meeting to solve site-clearance problems related to the HCMC-Long Thanh-Dau Giay expressway project.

Buổi làm việc của UBND tỉnh với Ban quản lý dự án đường cao tốc TP.Hồ Chí Minh - Long Thành - Dầu Giây.
A meeting between the province People's Committee and the authority for HCMC - Long Thanh - Dau Giay expressway project.

According to the authority for the project, the expressway may not be completed in time due to slow land handover. Presently, Long Thanh district’s Tam An and Long An communes still have not finished the site clearance work.

At the meeting, Chairman of People’s Committee Dinh Quoc Thai asked Long Thanh district’s authorities to carry out positive measures to complete site clearance and resettlement works to help secure construction of HCMC-Long Thanh-Dau Giay expressway as scheduled.

Reported by Q.K